L11b-A is ONE-Dyas’ manned offshore gas production and processing platform in the Dutch North Sea, approximately 65 kilometres north-northeast of Den Helder. The platform was originally installed for the L11b gas field and today also serves as the production hub for gas from the nearby L08-D and L11c-Gillian fields. The produced gas is exported through the North Gas Transport (NOGAT) pipeline to Uithuizen in the Netherlands.
Geology
The gas reservoirs in the L11 area are found in the Rotliegend formation. The L11b-A and L11c-Gillian fields contain mainly Upper Slochteren Sandstone reservoirs. The reservoirs are thin and compartmentalised, which influences how the gas can be produced over time.
The process
Gas from L08-D and L11c-Gillian is produced through several wells and processed on the L11b-A platform. Compression is used to support production as reservoir pressure declines. After processing, the gas is transported through the NOGAT pipeline to Uithuizen. A small proportion of the produced gas is used to provide energy for the platform itself.
History
The L11b-A platform was originally developed for production from the L11b field. The field was discovered in 1978 and has been in production since 1984. Over time, L11b-A developed into an important production hub for other gas fields in the area. L08-D was discovered in 2004 and achieved first gas in 2009. L11c-Gillian was discovered in 2015 and started production in the same year.
Safety and environment
Safe and responsible operations are a continuous priority throughout the life of L11b-A. As the platform has been operating for many years, ONE-Dyas continues to maintain and upgrade the facilities to meet current health, safety and environmental standards. Improvements have been made to increase efficiency, reduce fuel gas consumption and lower NOx and CO₂ emissions.